Chennai: Metro tunnelling completed between Ayanavaram and Otteri – ET Infra


File Photo

CHENNAI: A tunnel boring machine named Anaimalai completed tunnelling between Ayanavaram metro and Otteri metro on Thursday and achieved a breakthrough as part of the 116.1km phase-2 project

A release said Anaimalai, which started tunnelling on October 23, 2023, built a 925metre-long tunnel and reached the shaft at Otteri metro.

CMRL managing director M A Siddique and other officials were present during the breakthrough event.

The stretch from Ayanavaram to Otteri is part of the 9km underground section on the 45.4km corridor-3 from Madhavaram Milk Colony to Siruseri Sipcot. A total of seven tunnel boring machines have been mobilised for tunnelling work in the stretch.

Phase-2 has three corridors covering 116.1km. A total of 23 tunnel boring machines will be used for tunnelling work in the project.

  • Published On Jun 14, 2024 at 05:08 PM IST

Join the community of 2M+ industry professionals

Subscribe to our newsletter to get latest insights & analysis.

Get updates on your preferred social platform

Follow us for the latest news, insider access to events and more.



Source link

Leave a Comment

Your email address will not be published. Required fields are marked *

Open chat
1
How May I Help You.
Scan the code
Vishwakarma Guru Construction
Hello Sir/Ma'am, Please Share Your Query.
Call Support: 8002220666
Email: Info@vishwakarmaguru.com


Thanks!!